USMAI Aleph Patron Loader Implementation Steps

The following points are provided to help guide campuses through the patron loader implementation process. This is a general overview of the steps involved, the process for each campus may vary according to local implementation requirements.

Estimated implementation time–frame: Estimated duration of project is two weeks, depending upon the campus development needs.

  1. An implementation task group is established that includes at least one representative from the campus IT office, at least one from the library, and an ITD programmer, and the circulation systems librarian.

  2. ITD will schedule a conference call with the task group members to discuss the project and to clarify work responsibilities. The outcomes of the meeting will be: review and answer questions regarding the patron data format and file transfer specifications. A work timeline will also be established.

  3. A documentation packet is distributed to each member of the implementation task group that includes: the PeopleSoft v. 8 or 9 extract specs, the USMAI Patron Format, and Aleph Email Implementation Guide

    Decisions/work for the campus:

  4. Testing.



  5. Scheduling Loads.



  6. Automating loads