University System of Maryland and Affiliated Institutions
BINDERY PROCESSING
Contributed by Pamela Bluh 2004/11/12
Search title, select subscription – as for any other search – all items
checked in
Select Item List [M] from the tree in the left pane and highlight the
first item to be collapsed for binding; click Bind/Change
In the left window, highlight all the items to be collapsed in a group;
using the arrow key move the highlighted items into the right pane, and
click Bind
Modify the item to reflect the new item; change Enum. Level 1, Enum.
Level 2, and Description - as needed, and on Tab 4, zero out the Issue Date,
the Expected Arrival Date and the Arrival Date, click Update
The Item List indicates the volume is at the bindery; but the zeroed out dates do not "stick"; the Issue Date reverts to the date the collapsing is done; the Expected Arrival Date reverts to a date X number of days after the Issue Date (based on the claim interval from the Subscription); the Arrival Date remains at zero.
The display from the OPAC
Bindery "pull" slip - click on Completed Volumes and print